OUR PROJECTS

Papamoa College Redevelopment

Papamoa College expansion project for MOE with Stead Construction.

Aquaholics was engaged by Stead Construction to partner on the Papamoa College Redevelopment. The project consisted of three new major classroom blocks, a new administration block, a refit of an existing block, a new Whare, and associated carpark works. The civil drainage portion included stormwater, wastewater, gas mains, fire mains, and domestic water mains.

- Stormwater: Works included new sealed systems ranging from 375mm to 100mm PVC. The main line runs to new rainwater harvesting tanks with an overflow to a new 300m3 Cirtex RainSmart soakage system. We relocated existing stormwater infrastructure at depths of 3–3.5m using trench shields and dewatering. The scope also involved multiple manholes, cesspits, and pipework for new landscaping, as well as the construction of rain gardens and swales for carpark runoff.

- Sewer: We installed new sewer reticulation, including grease traps, manholes, and rod-eye (RE) points to service the new buildings. Existing main sewer lines were redirected at depths of 4m using trench shields and dewatering. A new 20m3 sewer pump station and storage system was installed at a depth of 5.7m, requiring sheet piling and dewatering. New rising main connections were then made to the boundary via a new manhole.

- Services Infrastructure: New 150mm fire and domestic water connections were installed from the TCC network to the school boundary. We constructed dedicated fire and domestic mains throughout the school to new building connections and hydrant locations.

- Gas: We upgraded the gas metering and main regulator station with new solenoid and seismic valves. New gas mains were run from existing blocks to the new technology block.